Puerto Vallarta Airport Projections for the years 2015-2019

Vallarta General News
Typography
  • Smaller Small Medium Big Bigger
  • Default Helvetica Segoe Georgia Times

airpBy 2019, the Puerto Vallarta International Airport expects to attract nearly 3.2 million passengers by 2029 more than 4 million, according to projections arising from the Master Development Program from 2015 to 2029, a period which includes investments more 602 million pesos, and was announced by Francisco Villaseñor Reyes, CEO of the airport terminal.

At the meeting of the Advisory Committee of the Airport "Gustavo Diaz Ordaz," led by the CEO of Pacific Airport Group (GAP), Fernando Bosque Mohino, the terminal manager, said that in 2013 it received 2,000,000 671,000 235 passengers, of whom 860,000 were domestic and 346 million international 810 000 889.

In this regard said that according to projections, this year 2 million 965 thousand passengers (937 000 600 national and international 2 million 27 thousand 800)

He noted that it is still a considerable distance to achieve best year figures on record, 2008, when 3 million 280 thousand 692, (511 domestic and 908 000 372 000 181 2 million international) passengers were received

At the same time, he said, based on a number of factors analyzed, including the global economy, an optimistic estimate is that by 2019 one million will receive 126 000 18 domestic passengers and 2 million 62 000 International 962, for a total 3 million 188 thousand 980., that is, and about what I achieved in 2008.

By 2024 the projection is to reach 3 million passengers 619 000 368 (1 million 349 thousand 898 national and international 2 million 269 000 470) and by 2029, based on projected to reach 4 million 60 thousand 873 passengers (1 million 585 thousand and 2 million domestic 961 474 000 913 international).

Regarding investments, Villaseñor Reyes explained that the airport infrastructure Vallarta now has the capacity to receive 7 million passengers per year, making investments over the next three-year periods is primarily to improve the quality of service and comfort passengers.

For the period 2015-2019 850 000 312 million pesos, will be invested as follows: In the line capacity and quality, expand the terminal building area rows of passengers for customs control, adjustments and improvements in buildings, expansion platform for general aviation, building concrete slabs in positions 9 to 16.

Added to this is expected to build a parking structure, adapt and renovate the space of Body Rescue Fire Fighting (CREI), parking platform for ground handling equipment for aircraft and building direct shoot between the street, and a FBO platform.

For projects which are carried out to comply with ICAO standards, including painting, approach lighting, etc..; also work on environmental measures; in the network adequacy fire extension bag taxis, road rehabilitation and expansion perimeter fencing and vehicle access and adequacy of sidewalks.

Other works would be pavement rehabilitation of commercial and general aviation platform, taxiways, adequacy of stormwater channels. Finally the renovation and purchase of vehicles and equipment.

In the period 2020-2024 the investment would be 162 million 511 thousand pesos, for the expansion of the last national waiting room in the national building, the installation of a fuel hydrant network, building a training room and enlargement Communications Center CREI, pavement rehabilitation and renovation and purchase of vehicles and equipment.

Finally, for the 2025-2029 five-year projection is to invest 126 million 679 thousand pesos, to undertake projects to comply with OACI standards, pavement rehabilitation and renovation and purchase of vehicles and equipment.

"It's a significant amount of money to invest, not grow too concerned capacity, because the currently have," he said.